7-18-18: Baker Engineering, Inc. today obtained approval for the 11th rebuild permit issued by the City of Ventura. Currently we have secured 36% of rebuild permits issued.
Concrete has been poured on 2 of our projects and grading is near completion on a 3rd. It is wonderful to see the hammers swinging on these projects.
Wednesday, July 18, 2018
Monday, July 9, 2018
7-5-18: Baker Engineering, Inc. secures the 10th Thomas Fire rebuild permit issued by the City of Ventura. Currently, 30% of the rebuild permits have been secured by Baker Engineering, Inc. and 3 more projects are currently in plan check. One step closer for one more family getting back in their home. It has been a pleasure working with such good people as the Bell family pictured here.
Thursday, June 14, 2018
Wednesday, May 30, 2018
As of 5/24/18 the City of Ventura has issued 3 building permits for complete rebuild projects, the 3rd of which was for a Baker Engineering, Inc. project. To date Baker Engineering, Inc. has obtained permits on 2 fire damage repairs and 1 complete rebuild with another complete rebuild currently in plan check and another to be submitted within days.
Friday, May 22, 2015
Completed Pipe Line Suspension Bridge
Finally getting some pics up of the completed pipeline suspension bridge. 241 foot span, 40 foot elevation drop from high end to low end.
View along axis of bridge, people in the pic for scale.
Locked gate to prevent adventurous hikers from crossing.
Note the wheels left in place which were used to feed the pipe across the canyon in sections as it was assembled.