Friday, October 19, 2018

10-19-18: Ten Thomas Fire projects currently permitted & two permits pending. Construction is currently progressing nicely on multiple homes in the Ondulando neighborhood.








Wednesday, August 1, 2018

8-1-18: Our 6th Thomas Fire permit has been secured. This is out of a total of 15 issued by the City of Ventura. We also submitted another project today.
 Framing progressing on what was our 1st issued permit.
Foundation excavations begun on what was our 4th permit.

Monday, July 23, 2018

Foundation in place & ready for slab pour on one of our projects. Framing to begin soon.
7-23-18: Our 5th project approved by the City of Ventura today! This is the 13th permit issued by the City. Baker Engineering, Inc. has now obtained 38% of the Thomas Fire permits issued.

Wednesday, July 18, 2018

7-18-18: Baker Engineering, Inc. today obtained approval for the 11th rebuild permit issued by the City of Ventura. Currently we have secured 36% of rebuild permits issued.

Concrete has been poured on 2 of our projects and grading is near completion on a 3rd. It is wonderful to see the hammers swinging on these projects.

Monday, July 9, 2018

7-5-18: Baker Engineering, Inc. secures the 10th Thomas Fire rebuild permit issued by the City of Ventura. Currently, 30% of the rebuild permits have been secured by Baker Engineering, Inc. and 3 more projects are currently in plan check. One step closer for one more family getting back in their home. It has been a pleasure working with such good people as the Bell family pictured here.